Residents of Ibadan, Oyo State, are set to experience temporary power disruptions as the Ibadan Electricity Distribution Company (IBEDC) undertakes facility relocations to accommodate ongoing road construction works.
According to a statement issued by IBEDC, a total of 22 communities will face daily power outages of approximately three hours from January 5 to January 9, 2026.
The affected neighborhoods include Alalubosa GRA, Ogunkola, Museum, Akinola Maja, FRIN, Forestry College, Lead City, Lead British, House 18, Eleventh House, Commissionaire, Nursing Home, Sunrise, Post Housing, AMI Complex, ODUA, Police Headquarters, Apampa, The Heavens, Blossom Heritage, Polo Club, and Baale Akintayo.
IBEDC manage power outages amid infrastructural projects
IBEDC attributed the planned outages to road construction along Foodco Road and Idi Isin, which necessitated the relocation of its power lines and distribution assets.
“Some feeders will be switched off for approximately three hours daily as a result of these relocation activities,” the company confirmed on its official Facebook page.
The power outage, while temporary, underscores the challenges faced by distribution companies (DisCos) in balancing infrastructure development with consistent electricity supply.
Relocation exercises are necessary to ensure public safety and prevent damage to electricity infrastructure during roadworks.
DisCos and their role in stabilizing electricity supply
The IBEDC notice comes amid a broader context of ongoing operational challenges within Nigeria’s electricity sector.
DisCos have continued to navigate issues ranging from infrastructural maintenance to national grid instabilities.
The December 29, 2025, national grid collapse, which caused widespread outages across Nigeria, remains a key reminder of the fragility of power supply and the importance of coordinated planning among operators.
According to industry analysts, the capacity of DisCos to manage localized outages efficiently during infrastructural projects is crucial for minimizing inconvenience to customers and ensuring that electricity supply remains reliable across the country.
DisCos upgrade infrastructure to support local communities
IBEDC emphasized that the relocation of facilities is part of routine operational adjustments aimed at improving service delivery.
These efforts include the installation of modern distribution equipment, feeder maintenance, and network expansion to meet the growing electricity demands of Ibadan’s urban and suburban communities.
The company further urged residents to remain patient and assured them that the temporary power interruptions were part of a short-term plan to safeguard electricity assets while maintaining overall grid stability.
DisCos and energy sector reforms in Nigeria
The power outage in Ibadan is part of a wider narrative of ongoing electricity sector reforms.
The Nigerian government and regulatory bodies, including the Nigerian Electricity Regulatory Commission (NERC), have emphasized the need for improved metering, feeder management, and network upgrades to enhance transparency, reduce losses, and improve revenue collection.

In line with these reforms, DisCos are deploying strategies such as prepaid metering, energy caps, and feeder-level monitoring to ensure customers are billed accurately while also preventing overloads during construction or maintenance works.
IBEDC ensure minimal disruption through strategic planning
IBEDC has taken measures to mitigate the impact of the outages by providing advance notices and carefully scheduling feeder shutdowns.
By restricting the outages to three hours daily, the distribution company aims to minimize inconvenience to households, commercial enterprises, and critical facilities such as hospitals and schools.
This proactive approach reflects a growing trend among DisCos to maintain customer trust, enhance operational transparency, and align with regulatory guidelines that mandate reliable power delivery while supporting national infrastructure projects.
As Nigeria continues to urbanize and expand its industrial base, DisCos are expected to play a critical role in ensuring stable electricity supply across communities.
Strategic planning for feeder maintenance, coordination with civil works projects, and investment in modern distribution technology are key to sustaining service reliability.
IBEDC’s announcement of the temporary outage in 22 Oyo communities demonstrates a balance between necessary infrastructure upgrades and the continuous provision of electricity.
By proactively managing power interruptions and maintaining clear communication with consumers, DisCos are contributing to long-term improvements in Nigeria’s electricity sector.
The temporary power outages in Ibadan serve as a reminder of the complexities involved in managing electricity distribution in urban areas, especially amid ongoing infrastructure projects.
With DisCos like IBEDC taking deliberate steps to minimize disruption and enhance service reliability, residents can expect improved electricity delivery in the coming months as relocations and network upgrades are completed.